Engineering, procurement, and construction of 1 unit of Gas Turbine Inlet-Air Cooling Systems
| project name | 
 Client  | 
project site | Turbine type | Approximate Power Increase (MW) | 
| Engineering, procurement, and construction of 1 unitٍ ٍof Gas Turbine Inlet-Air Cooling Systems | Tehran Power Generation Company | Tarasht Power Plant | H-25 | 
 5  | 
The gas unit of Tarasht power plant is of Hitachi type and the construction of the cooling system has been able to increase its production power to nearly 3 megawatts in the hot seasons of the year. One of the points of interest of this project is its design, construction and full implementation in a limited time, which was completely done by domestic experts and all the stages of its construction were done in domestic workshops.